Laterite Stone Masnory rate Analysis

    Laterite Stone masnory      
 (9" Thick) Laterite Stone masnory 1:6  (quntty for 100cft)
 items                Qntty/cft/kg    rate       amount     unit 
 Laterite Stone  180.00         15.00      2700.00   cft
 Sand               18.05            10.00     180.51      cft
 Cement           3.01              251.00   755.15
                                                           3635.67 100/cft
                                                           36.36
 Add Labour ( including curing)            19.00
                                                           55.36 
 Add contractor profit 10.00 %            5.54
                                                  Rate: 60.89 /cft        

           Material Calculations Part 
 Material analysis for 100 cft (9” wall) laterite work – Ratio: 1:6
 Size of laterite without mortar= 1'3"x0'9"x0'6"=  0.47cft
 No of laterite for 100 cft works = 170 nos+ Add 10 no As Wasteges=180 nos
 Total Volume of Laterite For 100Cft= 79.9 cft 
Volume of mortar =( 100.65 - 79.9) = 20.75 cft Add 1.5% Wastage 
 Dry Volume = 20.75X 1.5 = 21.06 cft 
 Ratio - 1:6 (Cement: Sand) = Sum of ratio = 7
 Cement = (21.06*1)/7= 3.00 cft 
 Sand =(21.06*6)/7= 18.05 cft      

             Labour Calculations Part      
 Mason 350 /Head  
 Helper 250 /Head    
 labour rate Analysis :     Quantity       Labour     Amount    
                                       35.00         600.00     17.14                      
                                                                         18.00/Cft    
 1mason+1Helper Can Do 35.25Cft Work/75no laterite Work
 1mason+2Helper Can Do 46.00Cft Work/100no laterite Work                        
 
                         